Replace a rusted 400 square metre roof without impacting manufacturing schedules

Synergy Construction Group was called on to replace an extremely rusted structural steel roof frame measuring 400 square meters without impacting on manufacturing within the drum reconditioning plant which ran 12 hours a day, six days a week. Our approach was to divide the roof into four different sections, cut the frame off the building and remove the roof by crane over weekends. We then rebuilt the roof frame and re-seated the roof all in a single weekend without impacting the plant’s ability to run at near full capacity. An additional challenge was the disrepair of the roof, it crumbled as it was removed, requiring the use of significant safe work methods. Nevertheless, the project was delivered on time and on budget.